Building works must not commence until a Principal Certifier (PC) has been appointed. It is the responsibility of the PC to ensure that a Construction Certificate or Complying Development Certificate has been issued for building works. The PC must certify that building works carried out in accordance with the approved plans and specifications will comply with the BCA.
The PC is also responsible for ensuring that any pre-conditions to the issue of a Construction Certificate or Complying Development Certificate have been met and that the payment of any fees or contributions has been paid.
The PC must also provide a Notice of Inspections which nominates each of the occasions where a registered certifier will be required to visit the building site throughout the course of construction. The Notice of Inspections may also list any required certificates or information that the PC requires in order to issue any Occupation Certificate.